August 6, 2026 Update:

    Today, August 6, the excavation crew will begin winching work behind the building as part of site preparation. Early next week, they’re scheduled to begin demolition of the existing parking lot. 🟢 Branch Status: Open

    July 30, 2026 Update:

      Tuesday, August 4: Construction crews will begin mobilizing equipment at the Holly Branch. Tuesday, August 4 – Wednesday, August 5: Crews will begin removing sections of the parking lot, primarily around the outer edges. 🟢 Branch Status: Open

      July 29, 2026 Update:

        Survey crews will be onsite Thursday, July 30, 2026 to stake and locate the water main in preparation for construction. This work is part of the planning process. 🟢 Branch Status: Open

        July 17, 2026 Update:

          Holly Branch Parking Lot Project Begins Late July/Early August 🟢 Branch Status: Open Construction Begins: Late July/Early August Estimated Duration: 6 weeks